Fire Station Electrical Upgrade – Maryport Fire Station

About this project

PSA provided support for a fire station electrical upgrade with design services, as part of the the refurbishment of Maryport Fire Station. The project focused on replacing ageing electrical infrastructure, lighting and associated building services. Meanwhile, firefighters needed continued access to the station and appliance bay whenever required. Therefore, we coordinated the works carefully to protect emergency response capability. This approach minimised disruption and maintained a safe environment throughout construction.

 

 

 


 

 

 

CLIENT: Cumberland Council

SERVICES: Electrical design and construction duties

LOCATION: Maryport, Cumbria

SECTOR: Public Sector: Blue-Light

 

 


 

 

CLIENT OBJECTIVES

The client required a fire station electrical upgrade to improve reliability, compliance and energy efficiency. However, Maryport Fire Station needed to remain available for emergency call-outs throughout the project. Therefore, crews required uninterrupted access to appliance bays and other operational areas. The programme also needed to accommodate retained firefighters arriving at short notice. This requirement applied during evenings, weekends and overnight periods.

 

OUR SOLUTION

PSA assessed the existing services infrastructure and developed a phased fire station refurbishment strategy. We incorporated temporary arrangements where required to maintain essential electrical services during installation. Additionally, we worked closely with the contractor and station representatives throughout the project. This coordination aligned each phase with operational requirements and emergency response needs. Finally, testing and commissioning confirmed system performance before each completed area returned to full use.

  • Replacement electrical installation works
  • Lighting upgrades incorporating energy-efficient LED technology
  • Emergency lighting improvements
  • Temporary service arrangements during system changeovers
  • Continued access to operational appliance areas
  • Phased installation around emergency response requirements
  • Testing and commissioning of new systems

 

THE OUTCOME

Maryport Fire Station gained modern, reliable building services while remaining available for operational use. Careful phasing protected emergency response capability throughout the refurbishment programme. Furthermore, the upgraded electrical systems improved safety, compliance and energy efficiency. The completed installation also supports stronger reliability and long-term asset performance.